CONGREGATION EILAT
:
Construction Updates
Steel Ledger installation - Completed
Instalation of Steel Ledgers is completed.
Jul 28, 2005, 09:13
CONGREGATION EILAT
:
Construction Updates
Steel Ledger installation - Continue
Ledger installation is comleted. Work continue in concrete walls
Jul 27, 2005, 12:21
CONGREGATION EILAT
:
Construction Updates
Steel Ledger installation
Steel Ledger are installed, ready for the installation of the steel beams.
Jul 23, 2005, 11:57
CONGREGATION EILAT
:
Construction Updates
Concrete walls and Lintel progress
Crew started form for lintel and total hight for the concrete pour walls.
Jul 21, 2005, 11:49
CONGREGATION EILAT
:
Construction Updates
Structural Steel delivered
Strctural steel is on site, crew started the installation pf ledgers.
Jul 19, 2005, 11:39
CONGREGATION EILAT
:
Construction Updates
Isolated pads poured.
Masonry crew poured all isolated pads for the columns.
Jul 17, 2005, 11:44
CONGREGATION EILAT
:
Construction Updates
Concrete pour walls.
Work commence on the concrete pour walls
Jul 15, 2005, 11:31
CONGREGATION EILAT
:
Construction Updates
Waterproofing update
Waterproofing finished first lift on rear wall.
Jul 12, 2005, 11:24
CONGREGATION EILAT
:
Construction Updates
Waterproofing started
Waterproofing crew started applying material. Will be a total of four coats.
Jul 8, 2005, 10:35
CONGREGATION EILAT
:
Construction Updates
Work progress at east and north side of the existing
Work progress at east and north side of the existing building. Work includes backfilling and compacting of storm drain; and form and pour of 2x2 catch basins, total of 3.
Jul 5, 2005, 10:27
|
|
 |

|