Front Page 
 
 PRESS RELEASES
 
 CASE STUDY
 
 THE LENDER CORNER
 
 CURRENT PROJECTS
 
 INDUSTRY NEWS
 
 E-learning Area
 
 CONGREGATION EILAT
 Construction Updates
 Construction Schedule
 
 ARTESIA WELL FAITH
Search

Front Page Last Updated: Jun 2nd, 2006 - 15:30:50


ARTESIA WELL FAITH
Block Wall - Update
Progress in the construction of the block wall. Update
May 31, 2006, 13:37

ARTESIA WELL FAITH
Block Wall - Update
This update is for the block wall at the parking lot. It is 60% conpleted.
May 25, 2006, 12:42

ARTESIA WELL FAITH
Block walls at parking lot
Work in progress for the construction of the block walls at the parking lot.
May 24, 2006, 11:48

ARTESIA WELL FAITH
Footings for the walls at parking lot
Completed pouring concrete footing for the masonry walls.
May 24, 2006, 11:18

ARTESIA WELL FAITH
Cedar St. Entrance
Cedar St. Entrance
May 18, 2006, 09:42

CONGREGATION EILAT : Construction Updates
Metal Joist and steel Beams I
Structural steel intalation continue.
Sep 3, 2005, 23:14

CONGREGATION EILAT : Construction Updates
Metal Joist and steel Beams
The installation of structural steel and metal joist is under way.
Aug 31, 2005, 23:01

CONGREGATION EILAT : Construction Updates
Perforated drain pipe and Backfilling
Construction crew installed perforated drain pipe, a conveyers was used to backfill the hill at the retainer wall.
Aug 19, 2005, 22:44

CONGREGATION EILAT : Construction Updates
Slab poured
Construction crew poured concrete slab.

Aug 17, 2005, 22:20

CONGREGATION EILAT : Construction Updates
Slab preparation
Construction crew is laying sand and placing the steel rebar to prepare the pad for the concrete slab.
Aug 12, 2005, 12:20

CONGREGATION EILAT : Construction Updates
Plumbing and Electrical work
Electrical conduits and drains installed
Aug 10, 2005, 11:41

CONGREGATION EILAT : Construction Updates
Steel beams and columns - Continue
Installation of structural steel continue. Great progress!
Aug 5, 2005, 09:53

CONGREGATION EILAT : Construction Updates
Concrete pour walls completed
Construction crew completed the concrete pour walls and installation of ledgers.
Aug 4, 2005, 09:42

CONGREGATION EILAT : Construction Updates
Steel beams and columns
Installation of steel beams and columns start
Aug 1, 2005, 09:27

CONGREGATION EILAT : Construction Updates
Grouting final lift on Masonry Walls
Masonry crew continue to work on grouting walls, after the ledgers are installed
Jul 29, 2005, 09:19

CONGREGATION EILAT : Construction Updates
Steel Ledger installation - Completed
Instalation of Steel Ledgers is completed.
Jul 28, 2005, 09:13

CONGREGATION EILAT : Construction Updates
Steel Ledger installation - Continue
Ledger installation is comleted. Work continue in concrete walls
Jul 27, 2005, 12:21

CONGREGATION EILAT : Construction Updates
Steel Ledger installation
Steel Ledger are installed, ready for the installation of the steel beams.
Jul 23, 2005, 11:57

CONGREGATION EILAT : Construction Updates
Concrete walls and Lintel progress
Crew started form for lintel and total hight for the concrete pour walls.
Jul 21, 2005, 11:49

CONGREGATION EILAT : Construction Updates
Structural Steel delivered
Strctural steel is on site, crew started the installation pf ledgers.
Jul 19, 2005, 11:39


Latest Headlines
PRESS RELEASES
ISBS’s Premier Internet Based Product
CASE STUDY
No articles available.
THE LENDER CORNER
No articles available.
CURRENT PROJECTS
No articles available.
INDUSTRY NEWS
Current Needs within the Marketplace
Market Analysis Breakdown By Customer
The Market
E-learning Area
How construction loans work
PROJECT CHECKLIST
CONGREGATION EILAT
Metal Joist and steel Beams I
Metal Joist and steel Beams
Perforated drain pipe and Backfilling
ARTESIA WELL FAITH
Block Wall - Update
Block Wall - Update
Block walls at parking lot