ARTESIA WELL FAITH
Block Wall - Update
Progress in the construction of the block wall. Update
May 31, 2006, 13:37
ARTESIA WELL FAITH
Block Wall - Update
This update is for the block wall at the parking lot. It is 60% conpleted.
May 25, 2006, 12:42
ARTESIA WELL FAITH
Block walls at parking lot
Work in progress for the construction of the block walls at the parking lot.
May 24, 2006, 11:48
ARTESIA WELL FAITH
Footings for the walls at parking lot
Completed pouring concrete footing for the masonry walls.
May 24, 2006, 11:18
ARTESIA WELL FAITH
Cedar St. Entrance
Cedar St. Entrance
May 18, 2006, 09:42
CONGREGATION EILAT
:
Construction Updates
Metal Joist and steel Beams I
Structural steel intalation continue.
Sep 3, 2005, 23:14
CONGREGATION EILAT
:
Construction Updates
Metal Joist and steel Beams
The installation of structural steel and metal joist is under way.
Aug 31, 2005, 23:01
CONGREGATION EILAT
:
Construction Updates
Perforated drain pipe and Backfilling
Construction crew installed perforated drain pipe, a conveyers was used to backfill the hill at the retainer wall.
Aug 19, 2005, 22:44
CONGREGATION EILAT
:
Construction Updates
Slab poured
Construction crew poured concrete slab.
Aug 17, 2005, 22:20
CONGREGATION EILAT
:
Construction Updates
Slab preparation
Construction crew is laying sand and placing the steel rebar to prepare the pad for the concrete slab.
Aug 12, 2005, 12:20
CONGREGATION EILAT
:
Construction Updates
Plumbing and Electrical work
Electrical conduits and drains installed
Aug 10, 2005, 11:41
CONGREGATION EILAT
:
Construction Updates
Steel beams and columns - Continue
Installation of structural steel continue. Great progress!
Aug 5, 2005, 09:53
CONGREGATION EILAT
:
Construction Updates
Concrete pour walls completed
Construction crew completed the concrete pour walls and installation of ledgers.
Aug 4, 2005, 09:42
CONGREGATION EILAT
:
Construction Updates
Steel beams and columns
Installation of steel beams and columns start
Aug 1, 2005, 09:27
CONGREGATION EILAT
:
Construction Updates
Grouting final lift on Masonry Walls
Masonry crew continue to work on grouting walls, after the ledgers are installed
Jul 29, 2005, 09:19
CONGREGATION EILAT
:
Construction Updates
Steel Ledger installation - Completed
Instalation of Steel Ledgers is completed.
Jul 28, 2005, 09:13
CONGREGATION EILAT
:
Construction Updates
Steel Ledger installation - Continue
Ledger installation is comleted. Work continue in concrete walls
Jul 27, 2005, 12:21
CONGREGATION EILAT
:
Construction Updates
Steel Ledger installation
Steel Ledger are installed, ready for the installation of the steel beams.
Jul 23, 2005, 11:57
CONGREGATION EILAT
:
Construction Updates
Concrete walls and Lintel progress
Crew started form for lintel and total hight for the concrete pour walls.
Jul 21, 2005, 11:49
CONGREGATION EILAT
:
Construction Updates
Structural Steel delivered
Strctural steel is on site, crew started the installation pf ledgers.
Jul 19, 2005, 11:39
|
|
|
|